Wis. Admin. Code Public Service Commission § PSC 184.06 - Emergency work

Current through March 28, 2022

In case of an emergency resulting from the failure of power supply or from fire, storm, or similar events, a utility may begin necessary repair work without receiving prior commission authorization. The utility shall promptly notify the commission of the emergency work and shall, within 30 days after commencing the work, furnish the commission with the information required under s. PSC 184.04(3).

Notes

Wis. Admin. Code Public Service Commission § PSC 184.06
CR 11-039: CR Register July 2012 No. 679, eff. 8-1-12.