Wis. Admin. Code Public Service Commission § PSC 184.06 - Emergency work
Current through March 28, 2022
In case of an emergency resulting from the failure of power supply or from fire, storm, or similar events, a utility may begin necessary repair work without receiving prior commission authorization. The utility shall promptly notify the commission of the emergency work and shall, within 30 days after commencing the work, furnish the commission with the information required under s. PSC 184.04(3).
Notes
The following state regulations pages link to this page.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.