Wis. Admin. Code Department of Transportation Trans 215.07 - Finding, determination and order
(1) After the
hearing specified in s.
Trans 215.06, the department shall make such investigation
as it considers necessary in order to make a decision. The investigation shall
be conducted in accordance with the provisions of s.
84.11(4),
Stats.
(2)
(a) The department shall evaluate and select
each proposed replacement project based on a weighted ranking of the following
elements:
1. Sufficiency rating
2. Rate score
3. Estimated remaining life
4. Hearing results and
5. Any other items determined to be
significant.
(b) The
department shall evaluate and measure the eligibility of each proposed new
bridge at a new location in the following manner:
1. Initially, in order to be considered for
financing under ch. Trans 215, the length must exceed 475 feet and the
estimated cost must exceed $5 million.
2. An economic analysis must result in
measurable benefits that exceed costs.
(c) Any project determined to qualify under
all requirements for a finding, determination and order will be scheduled for
preliminary engineering and construction within limits of available funding.
Note: State funding requirements over and above available dollars will be requested of the legislature with the department's biennial budget recommendation under appropriation s. 20.395(2) (aq), Stats.
(d) Projects funded by the legislature and
the local units of government as set forth in s.
84.11(5m),
Stats., will proceed to construction.