Wis. Admin. Code Public Service Commission PSC 111.56 - Expedited review

An applicant requesting expedited review of a high voltage transmission line application under s. 196.491(3b), Stats., shall include all of the following in its application:

(1) All the information required under s. PSC 111.55, except that the detailed information required under s. PSC 111.55(10) is required only for the route the applicant proposes to construct.
(2) Information and documentation describing in detail why the application should receive expedited review.