In this chapter:
(1)
"Cogeneration facility" means a type of electric generation facility that
simultaneously generates electrical power and useful heat from the same primary
fuel source.
(2) "Commission" means
the public service commission of Wisconsin.
(2m) "Constructing an electric transmission
line" means either of the following:
(a)
Installing new conductors, insulators, and structures.
(b) Adding an additional circuit to an
existing electric transmission line.
(3) "Distribution line" means an electric
line whose main function is to deliver energy from a distribution substation to
individual customers.
(4)
"Distribution substation" means an electric substation whose primary function
is to transform the voltage of incoming power to the primary distribution
voltage.
(5) "Electric energy
storage facility" means a supply facility that does not transform fuel or
energy into electricity, but stores electricity or power capable of being
transformed into electricity, including:
(a) A
magnetic energy storage system.
(b)
A battery.
(c) Pumped
water.
(6) "Electric
generation facility" means a physical plant used for generating electrical
power and includes multiple generating units installed over time as part of an
overall development project. It also includes situations, such as wind farms,
where multiple small generators are installed as part of a single, overall
project. In the case of multiple units at a single site or proximate sites, the
environmental review will be predicated on the total project rather than unit
by unit.
(7) "EA" means an
environmental assessment.
(8) "EIS"
means an environmental impact statement.
(9) "Human environment" means the natural or
physical environment and the relationship of people with that
environment.
(10) "kV" means
kilovolt.
(11) "MW" means
megawatt.
(12) "Person" has the
meaning specified in s.
990.01(26),
Stats. "Person" also includes the state of Wisconsin and its political
subdivisions.
(13) "Rebuilding an
electric transmission line" means modifying an existing electric transmission
line to increase its capacity to carry current at the same voltage, including
changing conductors, insulators or structures.
(14) "Scoping" means a process by which the
commission requests other agencies and the public to help identify major
environmental issues and how they will be addressed in an EIS.
(15) "Upgrading an electric transmission
line" means modifying an existing electric transmission line to increase its
capacity to carry current and increasing its voltage, including changing
conductors, insulators or structures.
(16) "WEPA" means the Wisconsin Environmental
Policy Act, chapter 274, section 1, laws of 1971, and s.
1.11,
Stats.