19 CFR Part 351, Annex III to Part 351 - Deadlines for Parties in Antidumping Investigations

Status message

There are 6 Updates appearing in the Federal Register for 19 CFR 351. View below or at eCFR (GPOAccess)
View PDF at GPO Pt. 351, Annex III
Annex III to Part 351—Deadlines for Parties in Antidumping Investigations
Day 1 Event Regulation
1 Indicates the number of days from the date of initiation. Most of the deadlines shown here are approximate. The actual deadline in any particular segment of a proceeding may depend on the date of an earlier event or be established by the Secretary.
2 Assumes that the Department sends out the questionnaire 5 days after the ITC vote and allows 7 days for receipt of the questionnaire from the date on which it was transmitted.
3 Assumes about 28 days between the preliminary determination and verification.
4 Assumes that the preliminary determination is published 7 days after issuance (i.e., signature).
0 days Initiation
37 days Application for an administrative protective order 351.305(b)(3)
50 days Country-wide cost allegation 351.301(d)(2)(i)(A) (20 days after date on which initial questionnaire was transmitted)
51 days 2 Notification of difficulty in responding to questionnaire 351.301(c)(2)(iv) (Within 14 days after date of receipt of initial questionnaire)
51 days Section A response None
67 days Sections B, C, D, E responses 351.301(c)(2)(iii) (At least 30 days after date of receipt of initial questionnaire)
70 days Viability arguments 351.301(d)(1) (40 days after date on which initial questionnaire was transmitted)
87 days Company-specific cost allegations 351.301(d)(2)(i)(B)
87 days Major input cost allegations 351.301(d)(3)
115 days Request for postponement by petitioner 351.205(e) (25 days or more before preliminary determination)
120 days Allegation of critical circumstances 351.206(c)(2)(i) (20 days before preliminary determination)
140 days (Can be extended) Preliminary determination 351.205(b)(1)
150 days Submission of ministerial error comments 351.224(c)(2) (5 days after release of disclosure documents)
155 days Submission of proposed suspension agreement 351.208(f)(1)(A) (15 days after preliminary determination)
161 days 3 Submission of factual information 351.301(b)(1) (7 days before date on which verification is to commence)
177 days 4 Request for a hearing 351.310(c) (30 days after date of publication of preliminary determination)
187 days Submission of publicly available information to value factors (NME's) 351.301(c)(3)(i) (40 days after date of publication of preliminary determination)
194 days Critical circumstance allegation 351.206(e) (21 days before final determination)
197 days (Can be changed) Request for closed hearing sessions 351.310(f) (No later than the date the case briefs are due)
197 days (Can be changed) Submission of briefs 351.309(c)(1)(i) (50 days after date of publication of preliminary determination)
202 days Submission of rebuttal briefs 351.309(d) (5 days after dealine for filing case briefs)
204 days Hearing 351.310(d)(1) (2 days after submission of rebuttal briefs)
215 days Request for postponement of the final determination 351.210(e)
215 days (Can be extended) Final determination 351.210(b)(1) (75 days after preliminary determination)
225 days Submission ministerial error comments 351.224(c)(2) (5 days after release of disclosure documents)
230 days Replies to ministerial error comments 351.224(c)(3) (5 days after filing of comments)
267 days Order issued 351.211(b)

Title 19 published on 2013-04-01

The following are only the Rules published in the Federal Register after the published date of Title 19.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-10-22; vol. 78 # 204 - Tuesday, October 22, 2013
    1. 78 FR 62417 - Import Administration; Change of Agency Name
      GPO FDSys XML | Text
      DEPARTMENT OF COMMERCE, International Trade Administration
      Final rule; nomenclature change.
      This rule is effective October 21, 2013.
      19 CFR Parts 351, 354, and 356

Title 19 published on 2013-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 19 CFR 351 after this date.

  • 2013-11-19; vol. 78 # 223 - Tuesday, November 19, 2013
    1. 78 FR 69322 - Modification of Regulations Regarding Time Limits for Submission of Information Pertaining to Requests for Sampling in Antidumping Duty Administrative Reviews
      GPO FDSys XML | Text
      DEPARTMENT OF COMMERCE, International Trade Administration
      Proposed rule; request for comments.
      To be assured of consideration, comments must be received no later than December 31, 2013.
      19 CFR Part 351