24 CFR 884.212 - Project completion.
prev | next
§ 884.212
Project completion.
(a) FmHA certifications upon completion.
Upon completion of the project, FmHA shall inspect the project and, if determined to be acceptable, submit to the HUD field office the following certifications:
(3)
There are no defects or deficiencies in the project other than punchlist items, or incomplete work awaiting seasonal opportunity;
(b) HUD review.
HUD shall promptly review the certifications submitted pursuant to paragraphs (a) and (b) of this section (see § 884.203(b) ).
(c) HUD acceptance.
If HUD determines from the review that the certifications are acceptable in accordance with these subparts, the project shall be accepted.
(d) Acceptance where defects or deficiencies reported.
If the only defects or deficiencies are punchlist items or incomplete items awaiting seasonal opportunity, the project may be accepted and the Contract executed. If the Owner fails to complete the items within a reasonable time to the satisfaction of HUD (and the PHA, if applicable), HUD may, after consultation with FmHA, upon 30 days notice to the Owner (and the PHA, if applicable), terminate the Contract and/or exercise its other rights thereunder or, if the Contract is with a PHA, cancel its approval of the Contract and require its termination and/or exercise its other rights under the Contract and the ACC.
Title 24 published on 2012-04-01
no entries appear in the Federal Register after this date.
This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.
This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].
It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.