§ 63.1344 Affirmative defense for exceedance of emission limit during malfunction.
In response to an action to enforce the standards set forth in paragraph § 63.1343(b) you may assert an affirmative defense to a claim for civil penalties for exceedances of such standards that are caused by malfunction, as defined at 40 CFR 63.2. Appropriate penalties may be assessed, however, if the respondent fails to meet its burden of proving all of the requirements in the affirmative defense. The affirmative defense shall not be available for claims for injunctive relief.
(a) To establish the affirmative defense in any action to enforce such a limit, the owners or operators of facilities must timely meet the notification requirements in paragraph (b) of this section, and must prove by a preponderance of evidence that:
(1) The excess emissions:
(i) Were caused by a sudden, short, infrequent, and unavoidable failure of air pollution control and monitoring equipment, process equipment, or a process to operate in a normal or usual manner, and
(ii) Could not have been prevented through careful planning, proper design or better operation and maintenance practices; and
(iii) Did not stem from any activity or event that could have been foreseen and avoided, or planned for; and
(iv) Were not part of a recurring pattern indicative of inadequate design, operation, or maintenance; and
(2) Repairs were made as expeditiously as possible when the applicable emission limitations were being exceeded. Off-shift and overtime labor were used, to the extent practicable to make these repairs; and
(3) The frequency, amount and duration of the excess emissions (including any bypass) were minimized to the maximum extent practicable during periods of such emissions; and
(4) If the excess emissions resulted from a bypass of control equipment or a process, then the bypass was unavoidable to prevent loss of life, severe personal injury, or severe property damage; and
(5) All possible steps were taken to minimize the impact of the excess emissions on ambient air quality, the environment and human health; and
(6) All emissions monitoring and control systems were kept in operation if at all possible; and
(7) Your actions in response to the excess emissions were documented by properly signed, contemporaneous operating logs; and
(8) At all times, the facility was operated in a manner consistent with good practices for minimizing emissions; and
(9) The owner or operator has prepared a written root cause analysis to determine, correct, and eliminate the primary causes of the malfunction and the excess emissions resulting from the malfunction event at issue. The analysis shall also specify, using best monitoring methods and engineering judgment, the amount of excess emissions that were the result of the malfunction.
(b) Notification. The owner or operator of the facility experiencing an exceedance of its emission limit(s) during a malfunction shall notify the Administrator by telephone or facsimile (FAX) transmission as soon as possible, but no later than two business days after the initial occurrence of the malfunction, if it wishes to avail itself of an affirmative defense to civil penalties for that malfunction. The owner or operator seeking to assert an affirmative defense shall also submit a written report to the Administrator within 30 days of the initial occurrence of the exceedance of the standard in § 63.1343(b) to demonstrate, with all necessary supporting documentation, that it has met the requirements set forth in paragraph (a) of this section.
[75 FR 55053, Sept. 9, 2010]

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-03-27; vol. 79 # 59 - Thursday, March 27, 2014
    1. 79 FR 17340 - National Emission Standards for Hazardous Air Pollutant Emissions: Group IV Polymers and Resins; Pesticide Active Ingredient Production; and Polyether Polyols Production
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final action is effective on March 27, 2014. The incorporation by reference of certain publications listed in this final rule was approved by the Director of the Federal Register as of March 27, 2014.
      40 CFR Part 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-07-02; vol. 79 # 127 - Wednesday, July 2, 2014
    1. 79 FR 37850 - National Emission Standards for Hazardous Air Pollutants: Off-Site Waste and Recovery Operations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Proposed rule.
      Comments. Comments must be received on or before August 18, 2014. A copy of comments on the information collection provisions should be submitted to the Office of Management and Budget (OMB) on or before August 1, 2014. Public Hearing. We do not plan to conduct a public hearing unless requested. If requested, we will hold a public hearing on July 17, 2014. To request a hearing, please contact the person listed in the following FOR FURTHER INFORMATION CONTACT section by July 14, 2014.
      40 CFR Part 63