Not later than 12 months after November 8, 2007, the Chief of Engineers shall establish benchmarks for determining the length of time it should take to conduct a feasibility study for a water resources project and its associated review process under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.). The Chief of Engineers shall use such benchmarks as a management tool to make the feasibility study process more efficient in all districts of the Corps of Engineers.
The Chief of Engineers shall establish, to the extent practicable, under paragraph (1) benchmark goals for completion of feasibility studies for water resources projects generally within 2 years. In the case of feasibility studies that the Chief of Engineers determines may require additional time based on the project type, size, cost, or complexity, the benchmark goal for completion shall be generally within 4 years.
The Secretary shall consolidate deep draft navigation expertise within the Corps of Engineers into a deep draft navigation planning center of expertise.
Not later than 60 days after the date of the consolidation required under subparagraph (A), the Secretary shall submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives a list of the grade levels and expertise of each of the personnel assigned to the center described in subparagraph (A).
Not later than 180 days after November 8, 2007, with respect to any report of the Chief of Engineers recommending a water resources project that is complete prior to November 8, 2007, the Secretary shall complete review of, and provide recommendations to Congress for, the report in accordance with paragraph (1).