41 U.S. Code § 4707 - Remission of liquidated damages

When a contract made on behalf of the Federal Government by the head of a Federal agency, or by an authorized officer of the agency, includes a provision for liquidated damages for delay, the Secretary of the Treasury on recommendation of the head of the agency may remit any part of the damages as the Secretary of the Treasury believes is just and equitable.

Source

(Pub. L. 111–350, § 3,Jan. 4, 2011, 124 Stat. 3799.)

Historical and Revision Notes
Revised Section Source (U.S. Code) Source (Statutes at Large)
4707
41:256a.
Sept. 5, 1950, ch. 849, § 10(a), 64 Stat. 591; Pub. L. 104–316, title II, § 202(u), Oct. 19, 1996, 110 Stat. 3845.

The table below lists the classification updates, since Jan. 3, 2012, for this section. Updates to a broader range of sections may be found at the update page for containing chapter, title, etc.

The most recent Classification Table update that we have noticed was Tuesday, August 13, 2013

An empty table indicates that we see no relevant changes listed in the classification tables. If you suspect that our system may be missing something, please double-check with the Office of the Law Revision Counsel.

41 USCDescription of ChangeSession YearPublic LawStatutes at Large

 

LII has no control over and does not endorse any external Internet site that contains links to or references LII.