16 CFR 1500.270 - Granting of authorization.

§ 1500.270 Granting of authorization.
(a) When authorization contemplated by§ 1500.269 is granted, the area office director shall notify the applicant in writing, specifying:
(1) The procedure to be followed:
(2) That the operations are to be carried out under the supervision of an officer of the Consumer Product Safety Commission or the Bureau of Customs, as the case may be;
(3) A time limit, reasonable in the light of the circumstances, for completion of the operations; and
(4) Such other conditions as are necessary to maintain adequate supervision and control over the article.
(b) Upon receipt of a written request for extension of time to complete such operations, containing reasonable grounds therefor, the area office director may grant such additional time as he deems necessary.
(c) An authorization may be amended upon a showing of reasonable grounds therefor and the filing of an amended application for authorization with the area office director.
(d) If ownership of a hazardous substance covered by an authorization changes before the operations specified in the authorization have been completed, the original owner will be held responsible, unless the new owner has executed a bond and obtained a new authorization. Any authorization granted under this section shall supersede and nullify any previously granted authorization with respect to the article.
Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 1500.270 Granting of authorization.

(a) When authorization contemplated by § 1500.269 is granted, the area office director shall notify the applicant in writing, specifying:

(1) The procedure to be followed:

(2) That the operations are to be carried out under the supervision of an officer of the Consumer Product Safety Commission or the Bureau of Customs, as the case may be;

(3) A time limit, reasonable in the light of the circumstances, for completion of the operations; and

(4) Such other conditions as are necessary to maintain adequate supervision and control over the article.

(b) Upon receipt of a written request for extension of time to complete such operations, containing reasonable grounds therefor, the area office director may grant such additional time as he deems necessary.

(c) An authorization may be amended upon a showing of reasonable grounds therefor and the filing of an amended application for authorization with the area office director.

(d) If ownership of a hazardous substance covered by an authorization changes before the operations specified in the authorization have been completed, the original owner will be held responsible, unless the new owner has executed a bond and obtained a new authorization. Any authorization granted under this section shall supersede and nullify any previously granted authorization with respect to the article.

Title 16 published on 2015-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 16 CFR Part 1500 after this date.

  • 2015-11-19; vol. 80 # 223 - Thursday, November 19, 2015
    1. 80 FR 72342 - Amendment To Clarify When Component Part Testing Can Be Used and Which Textile Products Have Been Determined Not To Exceed the Allowable Lead Content Limits; Delay of Effective Date and Extension of Comment Period
      GPO FDSys XML | Text
      CONSUMER PRODUCT SAFETY COMMISSION
      Direct final rule; delay of effective date and extension of comment period.
      The effective date for the direct final rule published October 14, 2015, at 80 FR 61729, is delayed from December 14, 2015, until January 13, 2016. The rule will be effective unless we receive a significant adverse comment. If we receive a significant adverse comment, we will publish notification in the Federal Register withdrawing this direct final rule before its effective date. The comment date is extended to December 14, 2015.
      16 CFR Parts 1109 and 1500