§ 39.11 Reliability reports.

(a) The Electric Reliability Organization shall conduct assessments as determined by the Commission of the reliability of the Bulk-Power System in North America and provide a report to the Commission and provide subsequent reports of the same to the Commission.

(b) The Electric Reliability Organization shall conduct assessments of the adequacy of the Bulk-Power System in North America and report its findings to the Commission, the Secretary of Energy, each Regional Entity, and each Regional Advisory Body annually or more frequently if so ordered by the Commission.

(c) The Electric Reliability Organization shall make available to the Commission, on a non-public and ongoing basis, access to the Transmission Availability Data System, Generator Availability Data System, and protection system misoperations databases, or any successor databases thereto. Such access will be limited to:

(1) Data regarding U.S. facilities; and

(2) Data that is required to be provided to the ERO.

[Order 672, 71 FR 8736, Feb. 17, 2006, as amended by Order 824, 81 FR 45008, July 12, 2016]

Title 18 published on 2015-08-22

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR Part 39 after this date.

  • 2016-07-12; vol. 81 # 133 - Tuesday, July 12, 2016
    1. 81 FR 44998 - Availability of Certain North American Electric Reliability Corporation Databases to the Commission
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      Effective date: This rule will become effective July 12, 2016. Compliance date: The compliance date is based on issuance of the final rule in Docket No. RM16-15-000. The Commission will publish a document in the Federal Register announcing the compliance date.
      18 CFR Part 39

Title 18 published on 2015-08-22.

The following are only the Rules published in the Federal Register after the published date of Title 18.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2016-07-12; vol. 81 # 133 - Tuesday, July 12, 2016
    1. 81 FR 44998 - Availability of Certain North American Electric Reliability Corporation Databases to the Commission
      GPO FDSys: XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      Effective date: This rule will become effective July 12, 2016. Compliance date: The compliance date is based on issuance of the final rule in Docket No. RM16-15-000. The Commission will publish a document in the Federal Register announcing the compliance date.
      18 CFR Part 39