§ 39.6 Conflict of a Reliability Standard with a Commission Order.

(a) If a user, owner or operator of the transmission facilities of a Transmission Organization determines that a Reliability Standard may conflict with a function, rule, order, tariff, rate schedule, or agreement accepted, approved, or ordered by the Commission with respect to such Transmission Organization, the Transmission Organization shall expeditiously notify the Commission, the Electric Reliability Organization and the relevant Regional Entity of the possible conflict.

(b) After notice and opportunity for hearing, within sixty (60) days of the date that a notice was filed under paragraph (a) of this section, unless the Commission orders otherwise, the Commission will issue an order determining whether a conflict exists and, if so, resolve the conflict by directing:

(1) The Transmission Organization to file a modification of the conflicting function, rule, order, tariff, rate schedule, or agreement pursuant to section 206 of the Federal Power Act, as appropriate, or

(2) The Electric Reliability Organization to propose a modification to the conflicting Reliability Standard pursuant to § 39.5 of the Commission's regulations.

(c) The Transmission Organization shall continue to comply with the function, rule, order, tariff, rate schedule, or agreement accepted, approved, or ordered by the Commission until the Commission finds that a conflict exists, the Commission orders a change to such provision pursuant to section 206 of the Federal Power Act, and the ordered change becomes effective.

[Order 672, 71 FR 8736, Feb. 17, 2006, as amended at 71 FR 11505, Mar. 8, 2006; Order 672-A, 71 FR 19823, Apr. 18, 2006]

Title 18 published on 2015-08-22

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 18 CFR Part 39 after this date.

  • 2016-07-12; vol. 81 # 133 - Tuesday, July 12, 2016
    1. 81 FR 44998 - Availability of Certain North American Electric Reliability Corporation Databases to the Commission
      GPO FDSys XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      Effective date: This rule will become effective July 12, 2016. Compliance date: The compliance date is based on issuance of the final rule in Docket No. RM16-15-000. The Commission will publish a document in the Federal Register announcing the compliance date.
      18 CFR Part 39

Title 18 published on 2015-08-22.

The following are only the Rules published in the Federal Register after the published date of Title 18.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2016-07-12; vol. 81 # 133 - Tuesday, July 12, 2016
    1. 81 FR 44998 - Availability of Certain North American Electric Reliability Corporation Databases to the Commission
      GPO FDSys: XML | Text
      DEPARTMENT OF ENERGY, Federal Energy Regulatory Commission
      Final rule.
      Effective date: This rule will become effective July 12, 2016. Compliance date: The compliance date is based on issuance of the final rule in Docket No. RM16-15-000. The Commission will publish a document in the Federal Register announcing the compliance date.
      18 CFR Part 39