19 CFR 113.42 - Time period for production of documents.

Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 113.42 Time period for production of documents.

Except when another period is fixed by law or regulations, any document for the production of which a bond or stipulation is given must be delivered within 120 days from the date of notice from CBP requesting such document, or within any extension of such time which may be granted pursuant to § 133.43(a). If the period ends on a Saturday, Sunday, or holiday, delivery on the next business day will be accepted as timely.

[T.D. 85-167, 50 FR 40363, Oct. 3, 1985, as amended by CBP Dec. 15-15, 80 FR 70167, Nov. 13, 2015]

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.

United States Code

Title 19 published on 2015-04-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 19 CFR Part 113 after this date.

  • 2015-11-13; vol. 80 # 219 - Friday, November 13, 2015
    1. 80 FR 70154 - Customs and Border Protection's Bond Program
      GPO FDSys XML | Text
      Final rule.
      Effective December 14, 2015.
      19 CFR Parts 101, 113, and 133