23 CFR 627.5 - Applicable projects.

§ 627.5 Applicable projects.
(a) A VE analysis shall be conducted prior to the completion of final design on each applicable project that utilizes Federal-aid highway funding, and all approved recommendations shall be included in the project's plans, specifications and estimates.
(b) Applicable projects shall include the following:
(1) Each project located on the National Highway System (NHS) (as specified in 23 U.S.C. 103) where the estimated total project cost is $25 million or more that utilizes Federal-aid highway funding;
(2) Each bridge project located on or off of the NHS where the estimated total project cost is $20 million or more that utilizes Federal-aid highway funding;
(3) Any major project (as defined in 23 U.S.C. 106(h)), on or off of the NHS, that utilizes Federal-aid highway funding in any contract or phase comprising the major project;
(4) Any project for which a VE analysis has not been conducted and a change is made to the project's scope or design between the final design and the letting which results in an increase in the project's total cost exceeding the thresholds identified in paragraphs (b)(1), (2) or (3) of this section; and
(5) Any other Federal-aid project the FHWA determines to be appropriate.
(c) An additional VE analysis is not required if, after conducting the VE analysis required under this part for any project meeting the criteria of paragraph (b) of this section, the project is subsequently split into smaller projects in the design phase or if the project is programmed to be completed by the letting of multiple construction projects. However, the STA may not avoid the requirement to conduct a VE analysis on an applicable project by splitting the project into smaller projects, or multiple construction projects.
(d) The STA's VE Program's policies and procedures shall identify when any additional VE analysis should be considered or conducted in the planning and development of transportation projects.
(e) For projects utilizing design-build and other alternative project delivery methods for which final design is not complete prior to the release of the final request for proposals or other applicable solicitation documents, the estimated total cost for purposes of the thresholds identified in paragraphs (b)(1) and (2) of this section, shall be based on the best estimate of the cost to construct the project.
Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 627.5 Applicable projects.

(a) A VE analysis shall be conducted prior to the completion of final design on each applicable project that utilizes Federal-aid highway funding, and all approved recommendations shall be included in the project's plans, specifications and estimates prior to authorizing the project for construction (as specified in 23 CFR 630.205).

(b) Applicable projects requiring a VE analysis shall include the following:

(1) Each project located on the National Highway System (NHS) (as specified in 23 U.S.C. 103) with an estimated total project cost of $50 million or more that utilizes Federal-aid highway funding;

(2) Each bridge project located on the NHS with an estimated total project cost of $40 million or more that utilizes Federal-aid highway funding;

(3) Any major project (as defined in 23 U.S.C. 106(h)), located on or off of the NHS, that utilizes Federal-aid highway funding in any contract or phase comprising the major project;

(4) Any project where a VE analysis has not been conducted and a change is made to the project's scope or design between the final design and the construction letting which results in an increase in the project's total cost exceeding the thresholds identified in paragraphs (b)(1), (2) or (3) of this section; and

(5) Any other project FHWA determines to be appropriate that utilizes Federal-aid highway program funding.

(c) An additional VE analysis is not required if, after conducting a VE analysis required under this part, the project is subsequently split into smaller projects in the design phase or the project is programmed to be completed by the letting of multiple construction projects. However, the STA may not avoid the requirement to conduct a VE analysis on an applicable project by splitting the project into smaller projects, or programming multiple design or construction projects.

(d) The STA's VE Program's policies and procedures should identify when VE analyses are to be considered or conducted for projects falling below the required thresholds identified in paragraph (b) of this section in the planning and development of transportation projects where there is a high potential for the project to benefit from a VE analysis. While not required, FHWA encourages STAs to consider the following projects that may benefit from a VE analysis:

(1) Complex projects on or off the NHS that have a total project cost of $25 million or more;

(2) Complex Bridge Projects on or off the NHS with an estimated total project cost of $20 million or more;

(3) Design-build projects on or off the NHS with an estimated cost of $25 million or more; and

(4) Any other complex, difficult or high cost project as determined by the STA.

(e) A VE analysis is not required for projects delivered using the design-build method of construction. While not required, FHWA encourages STAs and local public authorities to conduct a VE analysis on design-build projects that meet the requirements identified in paragraph (b) of this section.

(f) A VE analysis is required on projects delivered using the Construction Manager/General Contractor (CM/GC) method of contracting, if the project meets the requirements identified in paragraph (b) of this section.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code