§ 1926.706 Requirements for masonry construction.

(a) A limited access zone shall be established whenever a masonry wall is being constructed. The limited access zone shall conform to the following.

(1) The limited access zone shall be established prior to the start of construction of the wall.

(2) The limited access zone shall be equal to the height of the wall to be constructed plus four feet, and shall run the entire length of the wall.

(3) The limited access zone shall be established on the side of the wall which will be unscaffolded.

(4) The limited access zone shall be restricted to entry by employees actively engaged in constructing the wall. No other employees shall be permitted to enter the zone.

(5) The limited access zone shall remain in place until the wall is adequately supported to prevent overturning and to prevent collapse unless the height of wall is over eight feet, in which case, the limited access zone shall remain in place until the requirements of paragraph (b) of this section have been met.

(b) All masonry walls over eight feet in height shall be adequately braced to prevent overturning and to prevent collapse unless the wall is adequately supported so that it will not overturn or collapse. The bracing shall remain in place until permanent supporting elements of the structure are in place.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 29 published on 05-May-2017 03:24

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 29 CFR Part 1926 after this date.

  • 2017-03-21; vol. 82 # 53 - Tuesday, March 21, 2017
    1. 82 FR 14439 - Occupational Exposure to Beryllium; Further Delay of Effective Date
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Occupational Safety and Health Administration
      Final rule; further delay of effective date.
      As of March 21, 2017, the effective date of the final rule amending 29 CFR parts 1910, 1915, and 1926 that published in the Federal Register of January 9, 2017 at 82 FR 2470, delayed at 82 FR 8901 on February 1, 2017, is further delayed to May 20, 2017.
      29 CFR Parts 1910, 1915, and 1926

Pages