29 CFR Part 1926 - Subpart T - Demolition
- § 1926.850 Preparatory operations.
- § 1926.851 Stairs, passageways, and ladders.
- § 1926.852 Chutes.
- § 1926.853 Removal of materials through floor openings.
- § 1926.854 Removal of walls, masonry sections, and chimneys.
- § 1926.855 Manual removal of floors.
- § 1926.856 Removal of walls, floors, and material with equipment.
- § 1926.857 Storage.
- § 1926.858 Removal of steel construction.
- § 1926.859 Mechanical demolition.
- § 1926.860 Selective demolition by explosives.
Authority:
40 U.S.C. 3701; 29 U.S.C. 653, 655, 657; and Secretary of Labor's Orders 12-71 (36 FR 8754), 8-76 (41 FR 25059), 9-83 (48 FR 35736), 1-90 (55 FR 9033), 6-96 (62 FR 111), 5-2007 (72 FR 31159), or 1-2012 (77 FR 3912), as applicable.