30 CFR 250.201 - What plans and information must I submit before I conduct any activities on my lease or unit?

Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 250.201 What plans and information must I submit before I conduct any activities on my lease or unit?

(a) Plans and documents. Before you conduct the activities on your lease or unit listed in the following table, you must submit, and BSEE must approve, the listed plans and documents. Your plans and documents may cover one or more leases or units.

You must submit a(n) . . . Before you . . .
(1) [Reserved]
(2) [Reserved]
(3) [Reserved]
(4) Deepwater Operations Plan (DWOP), Conduct post-drilling installation activities in any water depth associated with a development project that will involve the use of a non-conventional production or completion technology.
(5) [Reserved]
(6) [Reserved]

(b) Submitting additional information. On a case-by-case basis, the Regional Supervisor may require you to submit additional information if the Regional Supervisor determines that it is necessary to evaluate your proposed plan or document.

(c) Limiting information. The Regional Director may limit the amount of information or analyses that you otherwise must provide in your proposed plan or document under this subpart when:

(1) Sufficient applicable information or analysis is readily available to BSEE;

(2) Other coastal or marine resources are not present or affected;

(3) Other factors such as technological advances affect information needs; or

(4) Information is not necessary or required for a State to determine consistency with their CZMA Plan.

(d) Referencing. In preparing your proposed plan or document, you may reference information and data discussed in other plans or documents you previously submitted or that are otherwise readily available to BSEE.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.

United States Code
U.S. Code: Title 31 - MONEY AND FINANCE
U.S. Code: Title 43 - PUBLIC LANDS

Title 30 published on 2015-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR Part 250 after this date.

  • 2015-12-04; vol. 80 # 233 - Friday, December 4, 2015
    1. 80 FR 75806 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Decommissioning Costs
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Final rule.
      This final rule becomes effective on January 4, 2016.
      30 CFR Part 250
The section you are viewing is cited by the following CFR sections.