30 CFR § 285.636 - What notices must I provide BSEE following approval of my COP?

prev | next
§ 285.636 What notices must I provide BSEE following approval of my COP?

You must notify BSEE in writing of the following events, within the time periods provided:

(a) No later than 30 days after commencing activities associated with the placement of facilities on the lease area under a Fabrication and Installation Report.

(b) No later than 30 days after completion of construction and installation activities under a Fabrication and Installation Report.

(c) At least 7 days before commencing commercial operations.