30 CFR 57.12017 - Work on power circuits.

Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 57.12017 Work on power circuits.

Power circuits shall be deenergized before work is done on such circuits unless hot-line tools are used. Suitable warning signs shall be posted by the individuals who are to do the work. Switches shall be locked out or other measures taken which shall prevent the power circuits from being energized without the knowledge of the individuals working on them. Such locks, signs, or preventive devices shall be removed only by the person who installed them or by authorized personnel.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.

United States Code

Title 30 published on 2015-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR Part 57 after this date.

  • 2015-09-02; vol. 80 # 170 - Wednesday, September 2, 2015
    1. 80 FR 52984 - MSHA Headquarters, Pittsburgh Safety and Health Technology Center, and Respirable Dust Processing Laboratory Address Changes
      GPO FDSys XML | Text
      DEPARTMENT OF LABOR, Mine Safety and Health Administration
      Final rule; technical amendment.
      Effective Date: September 2, 2015.
      30 CFR Parts 7, 18, 44, 46, 48, 49, 56, 57, 70, 71, 72, 74, 75, and 90