§ 154.1135 Response plan development and evaluation criteria.

The following response times must be used in determining the on scene arrival time in Prince William Sound for the response resources required by § 154.1045:

Tier 1 (hrs.) Tier 2 (hrs.) tier 3 (hrs.)
Prince William Sound Area 12 24 36