§ 147.2924 Area permits.

(a) Area permits may be issued for more than one injection well if the following conditions are met:

(1) All existing wells are described and located in the permit application;

(2) All wells are within the same well field, project, reservoir or similar unit;

(3) All wells are of similar construction; and

(4) All wells are operated by the same owner/operator.

(b) Area permits shall specify:

(1) The area within which injection is authorized; and

(2) The requirements for construction, monitoring, reporting, operation and abandonment for all wells authorized by the permit.

(c) Area permits can authorize the construction and operation of new wells within the permit area, if:

(1) The permittee notifies the Regional Administrator in the annual report of when and where any new wells have or will be drilled;

(2) The new wells meet the criteria outlined in paragraphs (a) and (b) of this section; and

(3) The effects of the new wells were addressed in the permit application and approved by the Regional Administrator.

Title 40 published on 2015-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR Part 147 after this date.

  • 2015-11-10; vol. 80 # 217 - Tuesday, November 10, 2015
    1. 80 FR 69629 - Request for Comment: Kentucky Underground Injection Control (UIC) Program; Primacy Approval
      GPO FDSys XML | Text
      Notice of public comment period and opportunity to request a public hearing.
      Comments will be accepted on or before December 23, 2015. Requests for a public hearing must be received by December 9, 2015. Requests for a hearing should be mailed to Nancy Marsh (see the FOR FURTHER INFORMATION CONTACT section). The EPA will determine by December 11, 2015, whether there is sufficient interest to warrant a public hearing. If determined to be warranted, the public hearing will be held on December 16, 2015 at 1:00 p.m. in Conference Room #D16 at the Department for Natural Resources, #2 Hudson Hollow, Frankfort, KY 40601. For additional information regarding the public hearing, please contact Nancy Marsh.