§ 63.546 Compliance dates.

(a) For affected sources that commenced construction or reconstruction on or before May 19, 2011, you must demonstrate compliance with the requirements of this subpart no later than January 6, 2014.

(b) For affected sources that commenced construction or reconstruction after May 19, 2011, you must demonstrate compliance with the requirements of this subpart by January 5, 2012 or upon startup of operations, whichever is later.

(c) Until the date specified in 63.546(a), secondary lead smelters that commenced construction or reconstruction on or before May 19, 2011, must continue to demonstrate compliance with the requirements of this subpart, codified in 40 CFR 63.541 through 40 CFR 63.550, that were in effect prior to the January 5, 2012, amendments. This means that secondary lead smelters that commenced construction or reconstruction on or before June 9, 1994, must continue to demonstrate compliance with existing source requirements of this subpart that were in effect prior to the January 5, 2012, amendments until the date specified in § 63.546(a). Secondary lead smelters that commenced construction or reconstruction after June 9, 1994, and on or before May 19, 2011, must continue to demonstrate compliance with new source requirements of this subpart that were in effect prior to the January 5, 2012, amendments until the date specified in § 63.546(a).

[ 77 FR 580, Jan. 5, 2012, as amended at 79 FR 371, Jan. 3, 2014]

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 10-May-2017 04:28

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR Part 63 after this date.

  • 2017-05-11; vol. 82 # 90 - Thursday, May 11, 2017
    1. 82 FR 21927 - Delegation of New Source Performance Standards and National Emission Standards for Hazardous Air Pollutants for the States of Arizona and Nevada
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule.
      This rule is effective on July 10, 2017 without further notice, unless EPA receives adverse comments by June 12, 2017. If we receive such comments, we will publish a timely withdrawal in the Federal Register to notify the public that this direct final rule will not take effect.
      40 CFR Parts 60, 61 and 63

Pages

The section you are viewing is cited by the following CFR sections.