40 CFR Appendix Table 2 to Subpart JJJJJ of Part 63, Operating Limits

Table 2 to Subpart JJJJJ of Part 63 - Operating Limits

As stated in § 63.8405, you must meet each operating limit in the following table that applies to you:

For each . . . You must . . .
1. Tunnel kiln equipped with a DLA a. Maintain the average pressure drop across the DLA for each 3-hour block period at or above the average pressure drop established during the HF/HCl/Cl2 performance test; or, if you are monitoring the bypass stack damper position, initiate corrective action within 1 hour after the bypass damper is opened allowing the kiln exhaust gas to bypass the DLA and complete corrective action in accordance with your OM&M plan; and
b. Maintain an adequate amount of limestone in the limestone hopper, storage bin (located at the top of the DLA), and DLA at all times; maintain the limestone feeder setting (on a per ton of fired product basis) at or above the level established during the HF/HCl/Cl2 performance test in which compliance was demonstrated; and
c. Use the same grade of limestone from the same source as was used during the HF/HCl/Cl2 performance test in which compliance was demonstrated; maintain records of the source and grade of limestone; and
d. Maintain no VE from the DLA stack.
2. Tunnel kiln equipped with a DIFF or DLS/FF a. If you use a bag leak detection system, initiate corrective action within 1 hour of a bag leak detection system alarm and complete corrective actions in accordance with your OM&M plan; operate and maintain the fabric filter such that the alarm is not engaged for more than 5 percent of the total operating time in a 6-month block reporting period; or maintain no VE from the DIFF or DLS/FF stack; and
b. Maintain free-flowing lime in the feed hopper or silo and to the APCD at all times for continuous injection systems; maintain the feeder setting (on a per ton of fired product basis) at or above the level established during the HF/HCl/Cl2 performance test for continuous injection systems in which compliance was demonstrated.
3. Tunnel kiln equipped with a WS a. Maintain the average scrubber liquid pH for each 3-hour block period at or above the average scrubber liquid pH established during the HF/HCl/Cl2 performance test in which compliance was demonstrated; and
b. Maintain the average scrubber liquid flow rate for each 3-hour block period at or above the highest average scrubber liquid flow rate established during the HF/HCl/Cl2 and PM/non-Hg HAP metals performance tests in which compliance was demonstrated.
4. Tunnel kiln equipped with an ACI system Maintain the average carbon flow rate for each 3-hour block period at or above the average carbon flow rate established during the Hg performance test in which compliance was demonstrated.
5. Tunnel kiln with no add-on control a. Maintain no VE from the stack.
b. Maintain the kiln process rate at or below the kiln process rate determined according to § 63.8445(g)(1).

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2015-08-22

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR Part 63 after this date.

  • 2017-04-06; vol. 82 # 65 - Thursday, April 6, 2017
    1. 82 FR 16736 - Mercury and Air Toxics Standards (MATS) Electronic Reporting Requirements
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on April 6, 2017.
      40 CFR Part 63