40 CFR Appendix Table 5 to Subpart FFF of Part 62 - Table 5 to Subpart FFF of Part 62—Generic Compliance Schedules and Increments of Progress
Affected facilities | Increment 1
Submit final control plan |
Increment 2
Award contracts |
Increment 3
Begin on-site construction |
Increment 4
Complete on-site construction |
Increment 5
Final compliance |
---|---|---|---|---|---|
Affected facilities that commenced construction modification, or reconstruction after June 26, 1987: | |||||
1. Emission limits for Hg, dioxin/furan | NA c | NA c | NA c | NA c | 11/12/99 or 1 year after permit issuance d e |
2. Emission limits for SO2, HCl, PM, Pb, Cd, opacity CO, NOX | January 11, 1999 | 05/18/99 | 11/16/99 | 11/19/00 | 12/19/00. |
a Table 4 or 5 of this subpart applies to MWC units subject to the Federal plan except those with site-specific compliance schedules shown in table 6 of this subpart.
b As an alternative to this schedule, the unit may close by December 19, 2000, complete retrofit while closed, and achieve final compliance upon restarting. See §§ 62.14108(c), 62.14108(d), and 62.14109(i) of this subpart.
c Because final compliance is achieved in 1 year, no increments of progress are required.
d Permit issuance is issuance of a revised construction permit or revised operating permit, if a permit modification is required to retrofit controls.
e Final compliance must be achieved no later than December 19, 2000, even if the date “1 year after permit issuance” exceeds December 19, 2000.