42 CFR 51b.605 - How will grant applications be evaluated and the grants awarded?

§ 51b.605 How will grant applications be evaluated and the grants awarded?

(a) Within the limits of funds available, the Secretary may award a grant to assist in meeting the costs of special activities authorized under section 318(b) of the Act.

(b) Grant applications will be reviewed and evaluated according to the following criteria:

(1) Is there adequate evidence that the proposed project is needed and that the outcome has potential to directly benefit the national venereal disease control effort?

(2) Are the project objectives specific, measurable, realistic, time phased, and related to promoting the purposes of section 318?

(3) Is the method of operation logical and clearly related to project objectives, and does it describe how the applicant intends to proceed particularly with activities which are complex, interrelated, or unprecedented?

(4) Does the method of operation include an assessment of any possible impact, both positive and negative, that the conduct of the proposed initiative might have upon the established venereal disease control program in the locality or localities in which the project will be undertaken?

(5) Does the proposal include a comprehensive and realistic plan for the evaluation of the project, and specify the measures and instruments of measurement to be used?

(6) Is the budget request reasonable and consistent with the intended use of grant funds?

(7) If the applicant intends only to evaluate an existing disease prevention and control approach, are the objectives substantially different from those which could be met by routine program evaluation?

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 42 published on 19-Apr-2017 03:51

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 42 CFR Part 51b after this date.

  • 2016-01-20; vol. 81 # 12 - Wednesday, January 20, 2016
    1. 81 FR 3004 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards; Technical Amendments
      GPO FDSys XML | Text
      DEPARTMENT OF HEALTH AND HUMAN SERVICES
      Interim final rule; technical amendments.
      Effective January 20, 2016. Implementation Date: For all non-Federal entities, there is a two-year grace period for implementation of the procurement standards in 45 CFR 75.326 through 75.335.
      42 CFR Parts 38, 50, 51, 51a, 51b, 51c, 51d, 52, 52a, 52b, 52c, 52d, 52e, 55a, 56, 57, 59, 59a, 62, 63a, 64, 65, 65a, 66, 67, 124, 136, 403, 417, 430, 433, 434, 435, 436, 438, 440, 441, 456, 457, and 1001