43 CFR 3273.20 - When will BLM release my bond?

§ 3273.20 When will BLM release my bond?
We will release your bond after you request it and we determine that you have:
(a) Removed the utilization facility and all associated equipment;
(b) Reclaimed the land; and
(c) Met all the requirements of § 3200.4.
Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 3273.20 When will BLM release my bond?

We will release your bond after you request it and we determine that you have:

(a) Removed the utilization facility and all associated equipment;

(b) Reclaimed the land; and

(c) Met all the requirements of § 3200.4.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 30 - MINERAL LANDS AND MINING
U.S. Code: Title 43 - PUBLIC LANDS
Public Laws