46 CFR 160.151-55 - Withdrawal of approval.

§ 160.151-55 Withdrawal of approval.

(a) The OCMI may withdraw the approval of the servicing facility, or may suspend its approval pending correction of deficiencies, if the Coast Guard inspector or accepted third-party inspector finds that -

(1) The facility does not meet the requirements of §§ 160.151-41 through 160.151-47, or

(2) The servicing is not performed in accordance with § 160.151-57.

(b) A withdrawal of approval may be appealed in accordance with part 1, subpart 1.03, of this chapter.

(c) The OCMI may remove a suspension pending correction of deficiencies if the servicing facility demonstrates that the deficiencies have been corrected.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Presidential Documents

Executive Order ... 12234

Title 46 published on 2015-12-02

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 46 CFR Part 160 after this date.

  • 2016-07-22; vol. 81 # 141 - Friday, July 22, 2016
    1. 81 FR 48220 - Harmonization of Standards for Fire Protection, Detection, and Extinguishing Equipment
      GPO FDSys XML | Text
      DEPARTMENT OF HOMELAND SECURITY, Coast Guard
      Final rule.
      This final rule is effective August 22, 2016. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register on August 22, 2016.
      33 CFR Parts 140, 145, 148, and 149