7 CFR 4280.16 - REDL and REDG Loan terms.

§ 4280.16 REDL and REDG Loan terms.

REDL and REDG loans made by the Intermediary are governed by the following terms:

(a) The maximum term of a loan is 10 years, including any principal deferment period. The Intermediary may choose a shorter term if desired.

(b) Deferments on Zero-Interest Loans will automatically be granted by Rural Development upon request of the Intermediary as follows:

(1) A deferral for up to 1 year for Projects involving an Established Operation; or

(2) A deferral for up to 2 years for Projects involving a Start-Up venture or a Community Facilities Project whether or not such Project also receives funding under USDA Community Facilities funding programs.

(c) The Intermediary must provide the Ultimate Recipient with the same loan terms as the Intermediary receives from Rural Development.

(d) The Intermediary is solely responsible for the financial approval of Fund loans and all other Fund decisions and actions.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 7 published on 2015-08-22

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 7 CFR Part 4280 after this date.

  • 2016-03-02; vol. 81 # 41 - Wednesday, March 2, 2016
    1. 81 FR 11000 - Environmental Policies and Procedures
      GPO FDSys XML | Text
      DEPARTMENT OF AGRICULTURE, Office of the Secretary, Rural Business-Cooperative Service, Rural Utilities Service, Rural Housing Service, Farm Service Agency
      Final rule.
      Effective date: The effective date for the final rule is April 1, 2016. Applicability date: For proposals that had a complete application submitted on or prior to April 1, 2016, either 7 CFR part 1794 or 7 CFR part 1940, subpart G, applies, as applicable. If the application was not complete prior to April 1, 2016, then 7 CFR part 1970 applies.
      7 CFR Part 25
The section you are viewing is cited by the following CFR sections.