7 CFR 4280.29 - Supplemental financing required for the Ultimate Recipient Project.

prev | next
§ 4280.29 Supplemental financing required for the Ultimate Recipient Project.

(a) For REDL loans, either the Ultimate Recipient or the Intermediary must provide supplemental funds for the Project equal to at least 20 percent of the loan to the Intermediary. For REDG grants, the Intermediary must provide supplemental funds, to capitalize the Revolving Loan Fund, equal to at least 20 percent of the Grant to the Intermediary.

(b) Funds provided by the Ultimate Recipient must be:

(1) Cash or its equivalent;

(2) Provided after Rural Development receives the completed application; and

(3) Disbursed for an eligible Project within a three year period that begins on the day the Intermediary signs the Grant agreement.

(c) Satisfactory evidence of the Ultimate Recipient's funds must be provided to Rural Development before it will advance any funds to the Intermediary.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 7 published on 2015-08-22

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 7 CFR Part 4280 after this date.

  • 2016-03-02; vol. 81 # 41 - Wednesday, March 2, 2016
    1. 81 FR 11000 - Environmental Policies and Procedures
      GPO FDSys XML | Text
      DEPARTMENT OF AGRICULTURE, Office of the Secretary, Rural Business-Cooperative Service, Rural Utilities Service, Rural Housing Service, Farm Service Agency
      Final rule.
      Effective date: The effective date for the final rule is April 1, 2016. Applicability date: For proposals that had a complete application submitted on or prior to April 1, 2016, either 7 CFR part 1794 or 7 CFR part 1940, subpart G, applies, as applicable. If the application was not complete prior to April 1, 2016, then 7 CFR part 1970 applies.
      7 CFR Part 25