Ala. Admin. Code r. 480-7-5-.07 - Preparation For Certificate Inspection
(1) The owner or user shall prepare each
boiler or pressure vessel for inspection and shall prepare for and apply a
hydrostatic or pressure test, whenever necessary, on the date arranged by the
inspector.
(2) The owner or user
shall prepare a boiler for internal inspection in the following manner:
(a) The fuel supply and ignition system shall
be locked out and/or tagged out in accordance with the owner/user's
procedures.
(b) Water shall be
drained off and the boiler washed thoroughly;
(c) Manhole and handhole plates, washout
plugs, and inspection plugs in water column connections shall be removed as
required by the inspector, and the furnace and combustion chambers shall be
cooled and thoroughly cleaned;
(d)
All grates of internally fired boilers shall be removed;
(e) Insulation or brickwork shall be removed
as required by the inspector in order to determine the condition of the boiler,
headers, furnace, supports, or other parts;
(f) The pressure gage shall be removed for
testing, as required by the inspector;
(g) Any leakage of steam or hot water into
the boiler shall be prevented by disconnecting the pipe or valve at the most
convenient point or by any appropriate means approved by the inspector;
and
(h) Before opening the manhole
or handhole covers and entering any parts of the steam generating unit
connected to a common header with other boilers, the non-return and steam stop
valves shall be closed, tagged, and padlocked, and drain valves or cocks
between the two valves opened. The feed valves shall be closed, tagged, and
padlocked. Blowoff lines, where practicable, shall be disconnected between
pressure parts and valves. All drains and vent lines shall be opened.
(3) Pressure vessels shall be
prepared for inspection to the extent deemed necessary by the inspector as
outlined herein.
(4) If a boiler or
pressure vessel has not been properly prepared for an internal inspection, or
if the owner or user failed to comply with the requirements for a pressure test
as set forth in these rules, the inspector may decline to make the inspection
or test, and the inspection certificate shall be withheld or suspended until
the owner or user complies with the requirements.
(5) If the boiler or pressure vessel is
jacketed so that the longitudinal seams of shells, drums, or domes cannot be
seen, sufficient jacketing, setting wall, or other form of casing or housing
shall be removed to permit reasonable inspection of the seams and other areas
necessary to determine the condition and safety of the boiler or pressure
vessel, provided such information cannot be determined by other
means.
(6) The shell or drum of a
boiler or pressure vessel in which a lap seam crack is discovered along a
longitudinal riveted joint shall be immediately discontinued from use. Patching
shall be prohibited.
(7) Pressure
Tests
(a) A hydrostatic pressure test, when
applied to boilers, shall not exceed 1-1/2 times the maximum allowable working
pressure. The pressure shall be under proper control so that in no case shall
the required test pressure be exceeded by more than six (6) percent.
(b) A hydrostatic pressure test, when applied
to pressure vessels, shall not exceed 1-1/2 times the maximum allowable working
pressure, except as permitted by the applicable ASME Code.
(c) During a hydrostatic test, the safety
valve or valves shall be removed or gagged; if gagged, each valve disk shall be
held to its seat by means of a testing clamp and not by screwing down the
compression screw upon the spring. A plug device designed for this purpose may
also be used.
(d) The minimum
temperature of the water used to apply a hydrostatic test shall be not less
than 70°F, and the maximum metal temperature during inspection shall not
exceed 120°F.
(e) When a
hydrostatic test is applied to determine tightness, the pressure shall be equal
to the normal operating pressure but need not exceed the release pressure of
the safety valve having the lowest release setting.
(f) When the contents of the vessel prohibit
contamination by any other medium or when a hydrostatic test is not possible,
other testing media may be used, providing the precautionary requirements or
the applicable sections of the ASME Code are followed.
(8) No employer (owner or user) shall permit
entry to, nor shall an employee or inspector enter, a boiler furnace, drum, or
header or pressure vessel until all requirements of the Occupational Safety and
Health Administration, Department of Labor,
29 CFR
1910.146 Permit-Required Confined Space
Standard, have been met and until the inspector or supervisor and the person
entering the boiler or pressure vessel have confirmed that all stop valves on
inlet and outlet piping not vented to the atmosphere have been closed and
tagged. Where not valved, the piping shall be disconnected or blanked. In
addition, plant personnel shall make appropriate tests to ensure that there are
no oxygen deficiencies or hazardous or toxic gases in the boiler furnace, drum,
or header or pressure vessel to be entered by the inspector. Prior to and
during entry, an approved person must be outside the boiler or pressure vessel
to ensure compliance with all confined space procedures.
Notes
Author: Board of Boilers & Pressure Vessels, Dr. David Dyer, Chairman
Statutory Authority: Code of Ala. 1975, §§ 25-12-4, -6, -14.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.