11 AAC 97.415 - Acreage to be bonded
(a) Acreage that must be bonded before a
mining operation begins in any calendar year is limited to any area to be mined
during that calendar year, plus any mined area (as that term is defined in
11 AAC 97.990) mined in a previous
year for which reclamation must be completed under this chapter; it is not
necessarily the same as the entire acreage of the mining operation. For an
underground mine, only the surface acreage disturbed by the operation
constitutes "mined area" for purposes of the bond requirement.
(b) After a multi-year reclamation plan goes
into effect, the miner shall ensure that the bond amount is sufficient at all
times to cover any area to be mined during the current calendar year, plus any
area mined in a previous year that has not yet been reclaimed.
(c) Any previously reclaimed area that is to
be mined again is subject to the bond requirement in the year that mining
resumes and until it is reclaimed.
(d) In calculating the number of acres that
must be bonded, a miner must round up to the next whole number.
Notes
Authority: Sec. 2, ch. 92, SLA
1990
AS 27.19.040
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.