18 AAC 70.910 - Compliance schedule
(a) If the department determines that more
time is required for a facility to come into full compliance with the water
quality standards under this chapter, and if the department determines that
allowing a facility more time to come into full compliance will not harm or
threaten public health or the environment, the department will include as a
condition of a permit, certification, or approval issued under this chapter, or
as a means for complying with water quality standards under this chapter, a
compliance schedule for a requirement
(1)
with which a facility is not in compliance when a permit or certification is
issued; or
(2) that becomes
effective during the life of a permit or certification and with which a
facility will not be in compliance.
(b) A compliance schedule issued under this
section must
(1) contain a narrative
description of how the facility will achieve compliance;
(2) include remedial measures specified as a
sequence of actions enforceable by the department, and with completion dates
leading to compliance for each requirement;
(3) require compliance in as brief a time as
feasible;
(4) if compliance is not
achievable in one year, include a schedule for the permittee to submit regular
progress reports to the department; a progress report submitted as required
under that schedule must include
(A) the
activities and completion dates required in the compliance schedule and the
dates when those activities were achieved; and
(B) an explanation of why a completion date
was not or cannot be met and a description of corrective measures
taken;
(5) include
requirements comparable to and at least as stringent as any compliance plan
requirement contained in a judicial consent decree or administrative order that
applies to the facility; and
(6)
include a statement that the compliance schedule does not prevent the
department from pursuing an enforcement action for noncompliance with a permit
condition not covered by the compliance schedule.
(c) The department will revise a compliance
schedule if the department determines that
(1) the permittee has shown good cause for
the revision;
(2) a shorter period
for achieving compliance is required to adequately protect water quality;
or
(3) a shorter period for
achieving compliance is feasible because one or more steps in the compliance
schedule become necessary or achievable in less time.
(d) A permittee who fails to comply with an
interim or final compliance date set out in a compliance schedule is in
violation of the permit, certification, or approval to which the compliance
schedule applies, and is subject to enforcement action by the department,
including modification, suspension, or revocation of the permit, certification,
or approval.
(e) A compliance
schedule included in an NPDES permit issued by EPA, or a revision of that
compliance schedule, is subject to federal regulations, including 40 C.F.R.
122.
Notes
Authority:AS 46.03.020
AS 46.03.050
AS 46.03.100
AS 46.03.110
AS 46.03.120
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.