18 AAC 71.050 - Processing of applications
(a) Availability of
grant money will be announced in legal and display advertisements in Alaska
newspapers of general circulation selected by the department. A mailing list
will be kept of all persons who ask to be on a mailing list. Persons on that
list will be given reasonable notice of grant availability.
(b) A person applying for a grant, or a
previous applicant who wishes to update or revise an application already on
file, shall submit the information required under
18 AAC 71.030 and
18 AAC 71.070 by February 15, 1985
to the water quality management section, Alaska Department of Environmental
Conservation, 3220 Hospital Drive, P.O. Box O, Juneau, Alaska 99811, Attn:
Mining Grants Program.
(c) Within
seven working days after receipt of an application, the department will review
it for completeness and will mail the applicant a certified letter stating that
the application is sufficient for review or that more information is
needed.
(d) Upon finding that an
application is sufficient for review, the department will send copies of it to
the committee for its review and recommendations.
(e) Within 30 days after closure of the
application period, the committee will evaluate all applications that it finds
complete and make a recommendation to the commissioner.
(f) If, upon its initial review of an
application, the committee finds it incomplete, the committee may request more
information from the applicant. Within 20 days after timely receipt of all
requested additional information, and no later than 60 days after the
application period ends, the committee will evaluate those applications for
which more information was requested and received.
(g) Within seven working days after receipt
and review of the committee's recommendation, the commissioner will approve or
deny the application. If the application is approved, the commissioner will
notify the applicant of the terms and conditions, including a schedule for
payment, and will make an offer of the grant. If the application is denied, the
commissioner will notify the applicant, stating reasons for denial.
(h) In his or her discretion, the
commissioner will withdraw any grant offer that is not accepted by the
applicant within 30 days.
(i) If a
grantee fails to accept a grant offer, the commissioner will, in his or her
discretion, award grant money to another eligible applicant after considering
the ratings applied by the committee.
Notes
Authority:AS 27.05.010
AS 46.03.020(10)
AS 46.16.060