18 AAC 72.010 - Permit and plan approval required
(a) Except for
systems exempted i from plan review under
18 AAC 72.511 or
18 AAC 72.611, a person who
disposes of wastewater in this state must have a plan approved by the
department and a permit issued by the department if the department requires a
permit under 18 AAC 83 for the disposal.
(b) The department may issue a plan approval
in lieu of a permit under this chapter if the department determines that
(1) the system meets the requirements of AS
46.03 and this chapter; and
(2) the
system is protective of public health, public and private water systems, and
the environment.
(c) The
department may consider a permit issued under 18 AAC 83 or 18 AAC 15 as the
plan approval required under
18 AAC 72.200 to modify a
previously approved wastewater treatment works and disposal system or to serve
as the approval to operate required under ISAAC 72.240.
(d) The applicant for or recipient of a
permit shall pay any fee for the permit as required under
18 AAC 72.956,
18 AAC 72.957, or
18 AAC
72.959.
Notes
Permit requirements previously included under 18 AAC 72.215 and 18 AAC 72.500 are now addressed in this section.
Authority:AS 44.46.020
AS 44.46.025
AS 46.03.020
AS 46.03.050
AS 46.03.100
AS 46.03.120