18 AAC 72.201 - Exceptions to prior written approval of engineering plans
(a) Prior written
approval of plans is not required for routine maintenance.
(b) Prior written approval of plans is not
required for repairs to address an emergency. The owner or operator shall
notify the department as required under
18 AAC 72.940.
(c) The department may evaluate a request to
replace a component of a wastewater collection, storage, treatment, or disposal
system with an equivalent component on a case-by-case basis.
(d) Prior written approval of plans is not
required for a sewer service line installation or modification that does not
affect the design capacity or result in the overloading of the wastewater
collection, treatment, or disposal system. The service line connection may not
result in the discharge of wastewater to a system that was not designed to
accept the volume or type of waste as approved or permitted by the department.
To qualify for this exception, the collection, treatment, and disposal system
to which the service line is connected must be owned by a local government
organization, or a private or public utility. If the service line is integral
to the design and operation of a collection system, this exception does not
apply.
(e) Prior written approval
of plans for installation or modification of a sewer main is not required for
an existing wastewater utility with a certified operator if the utility has
been issued an exception under this subsection as follows:
(1) to request an exception to prior written
plan approval to construct, install, renovate, or improve a collection system,
a wastewater utility must
(A) submit a written
application for the exception to the department;
(B) maintain current standards of
construction on file with and approved by the department;
(C) certify that the design and construction
of any sewer main installed under the exception will be completed in
conformance with the standards of construction described in (B) of this
paragraph;
(D) certify that the
utility will employ and maintain staff qualified to plan, design, construct,
operate, and inspect the sewer mains installed under the exception;
and
(E) maintain an updated list
with the names and professional qualifications of the staff proposed to design
and oversee installation of the sewer mains installed under this exception; the
department will make the final determination on whether the staff are
sufficiently qualified;
(2) if the department grants an exception
under this subsection, the department will notify the wastewater utility in
writing, specifying the scope and duration of the exception, any conditions for
maintaining the exception, and the date on or before which any application for
renewal must be submitted to the department;
(3) not later than December 31 of each year,
the wastewater utility must submit to the department an updated utility map or
set of engineering plans that highlights projects completed under the
exception;
(4) the department may
conduct periodic audits of the wastewater utility's oversight of projects that
began under the authority of this subsection;
(5) the department may deny or revoke the
exception granted under this subsection if the department determines that the
utility does not qualify for the exception, that the utility is not in
compliance with the terms of this subsection, or that the exception creates a
risk to public health.
Notes
Authority:AS 44.46.020
AS 46.03.010
AS 46.03.020
AS 46.03.050
AS 46.03.100
AS 46.03.110
AS 46.03.120
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.