18 AAC 75.402 - Delayed implementation dates
(a) If a person
applies for a new plan under
18 AAC 75.410, an amendment
determined to be a major amendment under
18 AAC 75.415(a),
or a plan renewal under
18 AAC 75.420, and that person
submits an application before August 4, 2023, the department will review the
application under
18 AAC 75.400 -
18 AAC 75.496, as those provisions
read on February 4, 2023.
(b) An
amendment application submitted before February 5, 2023 will be reviewed under
18 AAC 75.400 -
18 AAC 75.496, as those provisions
read on February 4, 2023, if the application
(1) is determined to be a minor amendment
under 18 AAC
75.415(a);
(2) is determined to be a routine update
submitted under
18 AAC 75.415(b);
or
(3) is for an amendment to allow
the addition of a vessel to an approved oil discharge prevention and
contingency plan under
18 AAC
75.415(c).
(c) A person submitting an application for a
new plan, major amendment, or plan renewal under (a) of this section may
request that the department instead review the application under the applicable
provisions of
18 AAC 75.400 -
18 AAC 75.496 in effect on
February 5, 2023.
(d) For a plan
approved by the department before February 5, 2023 or for a plan submitted and
approved under (a) of this section, before the expiration date listed on the
plan approval letter,
(1) the plan holder
must comply with
18 AAC
75.400(a)(2), if applicable and
18 AAC 75.400(j)
not later than February 5, 2023; and
(2) the plan holder is not required to submit
amendments to bring the plan into compliance with the requirements
(A) under
18 AAC
75.449(a)(6)(L);
(B) under
18 AAC
75.449(a)(6)(M) for procedures and
methods for wildlife protection, recovery, disposal, rehabilitation, and
release of wildlife to, as applicable, demonstrate best practices and
recommendations in the Alaska Regional Response Team Wildlife
Protection Guidelines for Oil Spill Response in Alaska, Version
2020.1, August 31, 2020; if approved by the department, the response strategies
may use alternative procedures and methods that adequately protect
wildlife;
(C) under
18 AAC
75.449(a)(8)(D);
(D) under
18 AAC
75.449(a)(9)(B);
(E) under
18 AAC
75.449(a)(10) to locate the
information on general procedures to be followed in responding to the greatest
possible discharge immediately following the response planning standard
scenario;
(F) under
18 AAC
75.451(b)(7);
(G) under
18 AAC
75.451(b)(8);
(H) under
18 AAC
75.451(h)(3);
(I) under
18 AAC
75.451(h)(4)(A) to determine the
necessary temporary storage capacity using the following formula: a system with
a manufacturer's rated throughput capacity (T) with a planned operating period
(U) requires temporary storage of T x U barrels per day to account for total
liquids recovered; and
(J) under
18 AAC 75.453(3)
to locate the required information in part five of the
plan.