18 AAC 76.220 - Priority list process
(a) To be eligible for financial assistance
from the Alaska drinking water fund, a project must be included on the Alaska
drinking water fund priority list of projects developed by the department.
Projects will be funded in accordance with the priority list, if money is
available. As part of its intended use plan required by
42 U.S.C.
300 j - 12(b), the department will establish
a proposed project priority list. The plan and list will be made available for
public review and comment for at least 30 days. After the public comment period
on the intended use plan and the project priority list closes, the department
may, based upon public comment, revise the proposed list. After receiving its
final priority list ranking, an applicant must resubmit a request under (b) of
this section each time the department issues a public notice of a proposed
revision to the project priority list. The deadline for submission of such
requests will be stated in the public notice. If an applicant fails to resubmit
a request by the stated deadline, the applicant's ranking is subject to change
or deletion.
(b) An applicant
seeking financial assistance from the Alaska drinking water fund must first
submit a request for a priority list ranking on a form provided by the
department.
(c) The department will
review priority list requests and will score the projects, using the following
criteria:
(1) the eligibility of the system
under 18 AAC 76.210, including the
applicant's operations, maintenance, and management capabilities;
(2) the eligibility of the project under
18 AAC 76.215;
(3) projects that address the most serious
risk to human health;
(4) projects
necessary to ensure compliance with the Safe Drinking Water Act and the Alaska
drinking water regulations, 18 AAC 80; and
(5) projects that assist systems most in need
of financial assistance that are cost-effective, on a per-household basis,
according to the affordability criteria established in the priority list
process under this section.
(d) The department will prepare a proposed
project priority list by ranking the projects scored under (c) of this section.
As required by 42 U.S.C.
300 j - 12(b), the department will include in
the intended use plan described in (a) of this section bypass criteria and
procedures for bypassing a project or accelerating the funding schedule for
another project.
Notes
Authority:AS 46.03.020
AS 46.03.036
AS 46.03.720