2 AAC 12.943 - Evaluation and award of design-build contracts
(a) The agency
shall use one or a combination of the following methods as a basis for award
unless the commissioner of transportation and public facilities approves
another method:
(1) the best value method, in
which the agency gives numerical scores to technical proposals, and then uses
those numerical scores and the bid price to establish a best value in
accordance with a formula published in the request for proposals;
(2) the two-step method, in which the agency
(A) first, uses a request for qualifications
and the qualification factors under
2 AAC 12.935 to short-list offerors; the request for
qualifications must contain, at a minimum, the following elements:
(i) the date on or before which the agency
must receive qualifications submissions; that date may not be less than 21 days
after issuance of the request for qualifications;
(ii) the qualifications the offerors will be
required to have;
(iii) a
description of the project in enough detail to let offerors determine if they
wish to compete and to form the basis for their qualification
submissions;
(iv) qualification
factors and their relative weights;
(v) identification of the maximum number of
offerors that will be permitted, at the second step described in (B) of this
paragraph, to submit price and technical proposals; the maximum number may not
exceed five offerors, unless the procurement officer determines that a maximum
number greater than five is in the best interest of the state; and
(B) second, uses a request for
proposals to evaluate price and technical proposals from the offerors that are
short-listed;
(3) the
low-bid method, in which
(A) an offeror must
submit a technically qualified proposal in order for the agency to consider the
bid; and
(B) the agency awards the
design-build construction contract to the offeror that submits a proposal that
is technically qualified and lowest price.
(b) If an agency uses a request for
qualifications to short-list offerors, the agency shall issue notice of the
request for qualifications in accordance with
2 AAC 12.130.
(c) To evaluate either submissions made in
response to a request for qualifications or submissions made in response to a
request for proposals, the agency may form evaluation committees. To assist in
the evaluation process, an evaluation committee may retain the services of
non-voting members, including consultants or subconsultants.
(d) An agency is not required to award a
design-build construction contract as a result of a request for proposals. In
accordance with
2 AAC 12.270,
2 AAC 12.860, and
2 AAC 12.870, the agency may reject a
proposal.
(e) Notice of intent to
award a design-build construction contract shall be issued in accordance with
2 AAC 12.210.
(f) The award of a design-build construction
contract, if any, shall be made in accordance with
AS
36.30.250.
(g) If the agency awards a design-build
construction contract, the agency shall execute the contract and issue the
successful offeror a written notice to proceed.
(h) At the time of award of a design-build
construction contract, the agency may negotiate minor changes with the selected
offeror for the purpose of clarifying the design criteria and work to be done,
if the negotiated changes do not affect the ranking of the proposals based on
their adjusted scores.
(i) In this
section,
(1) "short-list" means to narrow the
field of offerors through the selection of the most qualified offerors who have
responded to a request for qualifications;
(2) "technical proposal" means the portion of
a proposal that contains design solutions and other qualitative factors that
are provided in response to the request for proposals.
Notes
Authority:AS 36.30.040
AS 36.30.200
AS 36.30.350
AS 36.30.365