3 AAC 46.100 - Commission formation of an electric reliability organization
(a) The commission
will open a docket to form an electric reliability organization for an
interconnected bulk-electric system if
(1)
required under
AS
42.05.760(e);
(2) the certificate of the electric
reliability organization serving an interconnected bulk-electric system expires
under 3 AAC 46.050(b);
or
(3) the commission has revoked,
under 3 AAC 46.050(e),
the certificate of the electric reliability organization serving an
interconnected bulk-electric system.
(b) When it opens a docket under (a) of this
section, the commission will
(1) designate all
interconnected load-serving entities in the interconnected bulkelectric system
as parties to the docket;
(2)
permit an interested user, owner, or operator of the interconnected
bulkelectric system to become a party to the docket upon the filing of a notice
of participation; and
(3) allow
other interested persons to petition to intervene in the docket under the
procedures set out in
3
AAC 48.110.
(c) After an opportunity for the parties in
the docket to be heard, the commission will initiate formation of an electric
reliability organization for an interconnected bulk-electric system by
developing articles of incorporation under AS 10.20 as a nonprofit corporation
exempt from federal taxation under the United States Internal Revenue Code (26
U.S.C.), as that federal law exists at the time. The corporation's purpose is
to become the electric reliability organization of the interconnected
bulk-electric system, consistent with (i) of this section. The chair of the
commission shall appoint three commissioners to serve as interim directors.
Interim directors shall file the articles of incorporation, and serve as voting
directors of the nonprofit corporation, until they are replaced with directors
who are selected under the process required by (d) - (h) of this
section.
(d) The commission will
solicit applications from persons interested in serving as directors of the
corporation that will become the electric reliability organization for the
interconnected bulk-electric system. The commission will notify the general
public that applications for three positions as directors of the electric
reliability organization are being accepted. In the notice, the commission will
describe
(1) the minimum qualifications for
the director positions, including the qualifications set out in
3
AAC 46.460(a)(1);
(2) the application process and
requirements;
(3) the closing date
for applications; and
(4) the
selection process.
(e)
Applications must be accompanied by
(1) a
resume of the applicant's education and work experience; and
(2) a narrative explaining how the
applicant's education and work experience qualify the applicant to be an
effective director of the electric reliability organization.
(f) The commission will accept
applications only from persons who would qualify as independent directors under
3
AAC 46.070. The commission will return an application
of a person who does not qualify as an independent director under
3
AAC 46.070 to the applicant, with an explanation of
why the applicant does not qualify as an independent director. If the
commission determines that the number of qualified applicants is insufficient,
the commission will solicit additional applications.
(g) After the final closing date for
applications and a commission determination that the number of applications is
sufficient, the commission will notify the general public that comments are
being accepted on the applications received.
(h) After review of public comments and
interviews with applicants the commission will select three
directors.
(i) Upon selection of
directors by the commission under (h) of this section, the interim directors
shall appoint the persons selected by the commission to be directors of the
electric reliability organization and resign from their position as interim
directors. Upon the resignation of the interim directors and their replacement
by directors selected under (h) of this section, the commission will grant the
nonprofit corporation a certificate to be the electric reliability organization
of the interconnected bulk-electric system. Any amendments to or restatement of
articles of incorporation, or electric reliability organization bylaws or
rules, or modifications of those documents, that the electric reliability
organization seeks to adopt must be submitted to and approved by the commission
before being finalized.
(j) Not
later than 21 days after the date of the order announcing the commission's
selection, the directors shall meet to develop a proposed budget for organizing
the electric reliability organization. In the proposed budget, the directors
shall include the costs to develop the materials required for an applicant
under 3 AAC 46.090(a),
including director compensation, if any. The proposed budget must be filed in
the electric reliability organization docket established under (a) of this
section. After providing parties an opportunity to be heard on the proposed
budget, the commission may approve or modify the proposed budget. The electric
reliability organization may file for commission approval of an initial
surcharge to recover its budgeted costs. The requirements of
3
AAC 46.420 -
3
AAC 46.430 do not apply to the initial surcharge
filing.
(k) Not later than 180 days
after its budget is approved, the electric reliability organization shall file
the materials required of an applicant under
3
AAC 46.090(a). The commission may
open a new docket of investigation to consider a filing made under this
subsection.
(l) The commission may
waive or modify by order the requirements of this section, in whole or in part,
upon application and a showing of good cause or on the commission's own motion.
A waiver granted under this subsection does not limit the burden of an
applicant to prove the applicant's ability to comply with the requirements of
AS
42.05.762.
Notes
Authority:AS 42.05.141
AS 42.05.151
AS 42.05.760
AS 42.05.762
AS 42.05.767
AS 42.05.770