3 AAC 46.410 - Reliability standard fllings
(a) Each
reliability standard filing must include
(1) a
copy of the electric reliability organization board resolution authorizing the
proposed reliability standard;
(2)
a summary of the proposed reliability standard, including an explanation of how
it impacts the interconnected bulk-electric system, and what the proposed
reliability standard intends to accomplish;
(3) if a proposed reliability standard or
modification is based on a standard adopted by a recognized standard-setting
entity,
(A) a copy of the authoritative
standard on which the proposed reliability standard is based; and
(B) a summary explaining how and why the
proposed reliability standard differs from the standard on which it is
based;
(4) a narrative
indicating if the electric reliability organization is aware if the proposed
reliability standard or modification conflicts with a commission rule or
directive, or any federal standard, rule, or function;
(5) a proposed order that includes the
following items;
(A) how the proposed
reliability standard meets the requirements of
AS
42.05.765(a); and
(B) how the proposed reliability standard is
just, reasonable, not unduly discriminatory or preferential, and in the public
interest;
(6) a
statement setting out the users, owners, or operators to which the proposed
reliability standard would apply based on their impact on the reliability of
the interconnected electric energy transmission network;
(7) the proposed implementation plan, if
approved, including a proposed effective date;
(8) a penalty matrix that describes
(A) the violation type and severity
level;
(B) a range of penalties
that may associated with a violation of the standard; and
(C) if applicable, how a violation could
threaten grid stability;
(9) a statement on how the electric
reliability organization will monitor, ensure compliance with, and enforce the
proposed reliability standard; and
(10) procedures by which a registered entity
found in violation of the proposed reliability standard must take action to
come back into compliance, as needed.
(b) The commission may, upon petition or on
its own motion, open a docket of investigation for the purpose of reviewing
approved reliability standards for conflicts with a function, rule, tariff,
rate schedule, or agreement that the commission has also accepted, approved,
adopted, or ordered.
(c) If a
conflict is identified, the commission will issue an order giving notice to the
electric reliability organization of the nature of the conflict. The electric
reliability organization must resolve the conflict not later than 180 days
after the commission's order.
(d)
The resubmitted reliability standard must be filed as a compliance filing in
the docket of investigation.
(e)
Not later than 45 days after receipt of the resubmitted reliability standard,
the commission will issue a final order approving the resubmitted reliability
standard or return it for further revision. If the reliability standard
requires further revision, the commission may close the docket. In that
circumstance, a revised reliability standard must be submitted under a new
tariff letter.
(f) The commission
may extend the timelines in (c) and (e) of this section on its own motion or
for good cause shown.
Notes
Authority:AS 42.05.141
AS 42.05.151
AS 42.05.762
AS 42.05.765
AS 42.05.770
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.