3 AAC 48.070 - Formal proceedings

(a) Except as otherwise provided by 3 AAC 48.030 and 3 AAC 48.650, an application for a certificate of public convenience and necessity or electric reliability organization certificate or for the revision, sale, lease, rental, or inheritance of a certificate; or for the authority to acquire a controlling interest in a certificated public utility, electric reliability organization, or pipeline carrier; or any other application required by AS 42.05 or AS 42.06, will be docketed and considered in a formal proceeding.
(b) A tariff filing will not be docketed or considered in a formal proceeding unless it is suspended by order of the commission within the statutory notice period, or within the regulatory notice period set under 3 AAC 46.320 for an electric reliability organization.
(c) The commission may institute a formal proceeding in regard to any jurisdictional matter, either on its own motion or on complaint.
(d) An electric reliability organization rule or petition for a new or revised integrated resource plan under AS 42.05.780 will not be docketed or considered in a formal proceeding unless it is suspended by order of the commission within the regulatory notice period set under 3 AAC 46.260 for a new or revised integrated resource plan or 3 AAC 46.470 for an electric reliability organization rule.

Notes

3 AAC 48.070
Eff. 1/13/73, Register 44; am 6/29/84, Register 90; am 3/11/2022, Register 241, April 2022

Authority:AS 42.05.141

AS 42.05.151

AS 42.05.171

AS 42.05.241

AS 42.05.261

AS 42.05.271

AS 42.05.281

AS 42.05.770

AS 42.05.140

AS 42.06.260

AS 42.06.290

AS 42.06.300

AS 42.06.340

AS 42.06.400

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.