3 AAC 48.300 - Waiver of statutory notice period
(a) When a utility
or pipeline carrier includes in its tariff advice letter a request under
3
AAC 48.270(a)(6) for a tariff filing
to take effect before the end of the statutory notice period, the burden of
showing good cause for waiving statutory notice must be borne by the filing
utility or pipeline carrier.
(b) In
response to each request under (a) of this section, the commission may take one
of the following actions:
(1) deny the
request and require at least the statutory notice period to expire before
allowing the tariff filing to take effect;
(2) grant the requested effective date as
proposed in the tariff advice letter;
(3) allow the tariff filing to take effect
before the end of the statutory notice period but later than the requested
effective date proposed in the tariff advice letter;
(4) pending a public hearing, suspend the
operation of the tariff filing for a period not longer than that permitted
under AS
42.05.421 or
AS
42.06.400.
(c) The commission, on its own motion or for
good cause shown, may waive statutory notice and specify an effective date
before the end of the statutory notice period for
(1) tariffs of new utilities or pipeline
carriers and of utilities or pipeline carriers brought under regulation by
operation of law;
(2) tariff
filings covering services, facilities, or commodities not previously
furnished;
(3) tariff filings that
take effect by means of adoption notices; and
(4) tariffs filed to comply with orders of
the commission.
Notes
Authority:AS 42.05.141
AS 42.05.151
AS 42.05.411
AS 42.06.140(a)
AS 42.06.390
AS 42.06.400
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.