A. The Commission shall ensure that each
application that is submitted timely and proposes a project eligible for
funding from the Account is evaluated. After the applications are evaluated,
the Committee shall forward a recommended allocation plan to the Commission.
The Commission shall grant or deny funding within 90 days after the application
deadline.
B. If the Commission
determines that it needs additional information to facilitate its review of an
application, the Commission shall:
1. Request
the additional information from the applicant, or
2. Request the applicant to amend the
application.
C. The
Commission shall approve grant funding, in whole or in part, or deny funding
using standards referenced under A.R.S. §
41-2402
and R10-4-402(C).
D. The standards
referenced in subsection (C) include an assessment of whether the proposed
project:
1. Is directed toward a problem that
is demonstrated by statistical data;
2. Is designed to address the identified
problem;
3. Is a coordinated effort
among multiple approved agencies;
4. Has specific goals;
5. Has measurable objectives that relate to
the goals;
6. Has appropriate
methods for evaluating achievement of objectives;
7. Has a reasonable budget of allowable
expenses;
8. Has identified the
required matching funds;
9. Has
internal controls to monitor expenditure of Account funds; and
10. If the program was previously funded, all
grant requirements were met timely and there were no reportable deficiencies
during monitoring reviews.