Ariz. Admin. Code § R11-3-205 - Extension of Time to Initiate Reclamation
A. If the owner or operator of an exploration
operation or aggregate mining unit believes the conditions specified in A.R.S.
§
27-1226(B) are met, the responsible party for the
exploration operation or aggregate mining unit may submit a request for an
extension of time to begin reclamation. The responsible party shall submit the
request of an extension of time at least 45 days before the times specified in
A.R.S. §
27-1226(A).
B. Within 30 days after receiving a request
under subsection (A), the Inspector shall approve or disapprove the request and
send written notice of the decision to the responsible party. If the Inspector
fails to act on the request within 30 days after receiving the request, the
request shall be deemed approved.
C. If the Inspector disapproves a request
submitted under subsection (A), the Inspector shall include an explanation of
reasons for the disapproval in the written notice sent under subsection
(B).