Ariz. Admin. Code § R11-3-210 - Fees

As specifically authorized under A.R.S. § 27-1233, the Inspector establishes and shall collect the following fees:

1. Reclamation plan for an exploration operation: $1,565;
2. Substantial change to an approved exploration operation reclamation plan: $1,565 for up to 20 acres of disturbances, including testing plots or roadway disturbances, plus $20/acre when the change is greater than 10 percent or 20 acres, whichever is less;
3. Reclamation plan for aggregate mining unit or facility: $3,800 for up to 160 acres of disturbance plus $20/acre of additional disturbance; and
4. Substantial change to an approved aggregate mining unit or facility reclamation plan: $1,565 plus $20/acre when the change is greater than 10 percent or 20 acres, whichever is less.

Notes

Ariz. Admin. Code § R11-3-210
Adopted by final rulemaking at 25 A.A.R. 828, effective 5/11/2019.

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.