Ariz. Admin. Code § R11-3-502 - Estimating the Cost of Reclamation
A.
When submitting estimated costs to perform a proposed reclamation, as required
under A.R.S. §§
27-1271(B)(11) and
27-1292,
the responsible party shall ensure the estimate equals the amount necessary for
a third party to perform each proposed reclamation measure listed in the
proposed reclamation plan. The responsible party shall ensure the estimate
includes:
1. Itemized calculation of
estimated cost to perform all reclamation measures for each category of mining
activity;
2. Documentation
demonstrating how the estimated cost for each category of mining activity,
including subtotals and totals, was calculated; and
3. Identification of the source of
information used to estimate each cost.
B. In estimating the cost of executing the
reclamation plan, all activities in the reclamation plan shall be addressed,
including, if applicable:
1. Earth moving,
regrading, and stabilization of surface disturbances and slopes;
2. Revegetation preparation of seedbed, and
planting or other stabilization methods;
3. Demolition of buildings and other
structures not to remain after cessation of mining;
4. Removal of trash, scrap metal, and other
materials;
5. Equipment
mobilization and demobilization
6.
On-going activities required to maintain the effectiveness of reclamation and
stabilization or in place of reclamation. This includes periodic clean-out of
sediment basins and maintenance of signs, berms, and fences used to prevent
access to areas that pose a threat to public safety;
7. Contractor profit; and
8. Administrative overhead.
C. The Inspector shall review the
estimated costs submitted under subsection (A) and determine whether the
estimate is adequate to complete all required reclamation. The Inspector shall
use the estimated costs to determine the amount of required financial
assurance.
D. If the Inspector
determines the estimated costs submitted under subsection (A) are inadequate to
complete all required reclamation, the Inspector shall deem the reclamation
plan incomplete under A.R.S. §§
27-1252
or
27-1272.