Ariz. Admin. Code § R12-7-105 - Change of Location
A. No
operator shall drill a well in a location other than that authorized by the
permit issued pursuant to
R12-7-104 until the following requirements have been met:
1. If the operator decides to change the
location before drilling the well, an amended application for permit to drill
shall be filed showing the new location.
2. If it is determined that the location is
erroneously described on the permit after drilling has begun, the operator
shall obtain a new permit showing the correct location.
B. If the new location is at an authorized
point in the approved drilling unit as provided in the initial permit, the
application may be made by electronic communication and the Commission may by
electronic communication authorize the commencement or continuance of drilling
operations. Within ten days after obtaining such authorization, the operator
shall file an amended application showing the new location. An amended permit
may be issued and the old permit cancelled without payment of additional
fee.
C. If the new location is
located outside the approved drilling unit covered by the initial permit, no
drilling shall be commenced or continued until a new application for permit to
drill is filed and approved as required by
R12-7-104,
including payment of an additional fee.