The following provisions apply to all injection projects defined in R12-7-175:
1. The operator shall notify the Commission
of the date that injection operations will begin.
2. The operator shall notify the Commission
of the date that injection operations will cease and provide the reasons for
discontinuing the injection operations.
3. An injection well shall not be
transferred from 1 operator to another without the written approval of the
Commission.
a. The operator shall file the
request for transfer of ownership of an injection well in triplicate with the
Commission at least 45 days before the proposed transfer date. The request
shall include the name, address, and telephone number of the proposed new
operator and provide the location and status of each well involved.
b. The proposed new operator shall file with
the Commission an organization report as required in
R12-7-194 and bond as required in
R12-7-103 before
the request for transfer will be considered.
c. The Commission shall return 1 copy of the
request for transfer to the operator and 1 to the proposed new operator within
30 days after receipt of the information required in subsections (3)(a) and
(b), designating approval or denial of the transfer of authority to inject for
the subject well.
i. If the proposed transfer
is approved, a copy of the order authorizing injection shall be attached to the
approved request for transfer.
ii.
If the proposed transfer is denied, the Commission shall return 1 copy of the
request to the operator and 1 copy to the proposed operator together with the
reasons for the denial and the steps necessary for its approval.