Ariz. Admin. Code § R14-2-207 - Line Extensions
A. General
requirements
1. Each utility shall file, in
Docket Control, for Commission approval, a line extension tariff which
incorporates the provisions of this rule and specifically defines the
conditions governing line extensions.
2. Upon request by an applicant for a line
extension, the utility shall prepare, without charge, a preliminary sketch and
rough estimate of the cost of installation to be paid by said
applicant.
3. Any applicant for a
line extension requesting the utility to prepare detailed plans,
specifications, or cost estimates may be required to deposit with the utility
an amount equal to the estimated cost of preparation. The utility shall, upon
request, make available within 90 days after receipt of the deposit referred to
above, such plans, specifications, or cost estimates of the proposed line
extension. Where the applicant authorizes the utility to proceed with
construction of the extension, the deposit shall be credited to the cost of
construction; otherwise the deposit shall be nonrefundable. If the extension is
to include oversizing of facilities to be done at the utility's expense,
appropriate details shall be set forth in the plans, specifications and cost
estimates. Subdivisions providing the utility with approved plats shall be
provided with plans, specifications, or cost estimates within 45 days after
receipt of the deposit referred to above.
4. Where the utility requires an applicant to
advance funds for a line extension, the utility shall furnish the applicant
with a copy of the line extension tariff of the appropriate utility prior to
the applicant's acceptance of the utility's extension agreement.
5. All line extension agreements requiring
payment by the applicant shall be in writing and signed by each
party.
6. The provisions of this
rule apply only to those applicants who in the utility's judgment will be
permanent customers of the utility. Applications for temporary service shall be
governed by the Commission's rules concerning temporary service
applications.
B. Minimum
written agreement requirements
1. Each line
extension agreement shall, at a minimum, include the following information:
a. Name and address of applicant or
applicants;
b. Proposed service
address or location;
c. Description
of requested service;
d.
Description and sketch of the requested line extension;
e. A cost estimate to include materials,
labor, and other costs as necessary;
f. Payment terms;
g. A concise explanation of any refunding
provisions, if applicable;
h. The
utility's estimated start date and completion date for construction of the line
extension; and
i. A summary of the
results of the economic feasibility analysis performed by the utility to
determine the amount of advance required from the applicant for the proposed
line extension.
2. Each
applicant shall be provided with a copy of the written line extension
agreement.
C. Line
extension requirements. Each line extension tariff shall include the following
provisions:
1. A maximum footage or equipment
allowance to be provided by the utility at no charge. The maximum footage or
equipment allowance may be differentiated by customer class.
2. An economic feasibility analysis for those
extensions which exceed the maximum footage or equipment allowance. Such
economic feasibility analysis shall consider the incremental revenues and costs
associated with the line extension. In those instances where the requested line
extension does not meet the economic feasibility criteria established by the
utility, the utility may require the customer to provide funds to the utility,
which will make the line extension economically feasible. The methodology
employed by the utility in determining economic feasibility shall be applied
uniformly and consistently to each applicant requiring a line
extension.
3. The timing and
methodology by which the utility will refund any advances in aid of
construction as additional customers are served off the line extension. The
customer may request an annual survey to determine if additional customers have
been connected to and are using service from the extension. In no case shall
the amount of the refund exceed the amount originally advanced.
4. All advances in aid of construction shall
be noninterest bearing.
5. If after
five years from the utility's receipt of the advance, the advance has not been
totally refunded, the advance shall be considered a contribution in aid of
construction and shall no longer be refundable.
D. Residential subdivision development and
permanent mobile home parks. Each utility shall submit as a part of its line
extension tariff separate provisions for residential subdivision developments
and permanent mobile home parks.
E.
Single phase underground extensions in subdivision developments
1. Extensions of single phase electric lines
necessary to furnish permanent electric service to new residential buildings or
mobile homes within a subdivision, in which facilities for electric service
have not been constructed, for which applications are made by a developer shall
be installed underground in accordance with the provisions set forth in this
rule except where it is not feasible from an engineering, operational, or
economic standpoint.
2.
Rights-of-way easements
a. The utility shall
construct or cause to be constructed and shall own, operate, and maintain all
underground electric distribution and service lines along public streets,
roads, and highways and on public lands and private property which the utility
has the legal right to occupy.
b.
Rights-of-way and easements suitable to the utility must be furnished by the
developer at no cost to the utility and in reasonable time to meet service
requirements. No underground electric facilities shall be installed by a
utility until the final grades have been established and furnished to the
utility. In addition, the easement strips, alleys and streets must be graded to
within six inches of final grade by the developer before the utility will
commence construction. Such clearance and grading must be maintained by the
developer during construction by the utility.
c. If, subsequent to construction, the
clearance or grade is changed in such a way as to require relocation of the
underground facilities or results in damage to such facilities, the cost of
such relocation or resulting repairs shall be borne by the developer.
3. Installation of single phase
underground electric lines within a subdivision
a. The developer shall provide the trenching,
backfill (including any imported backfill required), compaction, repaving, and
any earthwork for pull boxes and transformer pad sites required to install the
underground electric system all in accordance with the specifications and
schedules of the utility.
b. Each
utility shall inspect the trenching provided by the developer within 24 hours
after a mutually agreed upon trench opening date, and allow for phased
inspection of trenching as mutually agreed upon by the developer and utility.
In all cases, the utility shall make every effort to expedite the inspection of
developer provided trenching. The utility shall assume responsibility for the
trench within three working days after the utility has inspected and approved
the trenching.
c. The utility shall
install or cause to be installed underground electric lines and related
equipment with sufficient capacity and suitable materials that ensure adequate
and reasonable electric service in the foreseeable future and in accordance
with the applicable provisions of Institute of Electrical and Electronic
Engineers, Inc., Pub. No. C2-2007, The National Electrical Safety Code (2007),
including no future editions or amendments, which is incorporated by reference,
on file with the Commission, and published by and available from the Institute
of Electrical and Electronic Engineers, Inc., 3 Park Avenue, 17th Floor, New
York, New York 10016, and through http://ieeexplore.ieee.org.
d. Underground service lines from underground
residential distribution systems shall be owned, operated and maintained by the
utility, and shall be installed pursuant to its effective underground line
extension and service connection tariffs on file with the Commission.
4. Special conditions
a. When the application of any of the
provisions of subsection (E) appears to either party not to be feasible from an
engineering, operational, or economic standpoint, the utility or the developer
may refer the matter to the Commission for a determination as to whether an
exception to the underground policy expressed within the provisions of this
rule is warranted. Interested third parties may present their views to the
Commission in conjunction with such referrals.
b. Notwithstanding any provision of this
regulation to the contrary, no utility shall construct overhead single phase
electric lines in any new subdivision to which this rule is applicable and
which is contiguous to another subdivision in which electric service is
furnished underground without the approval of the Commission.
c. Underground service lines installed
pursuant to subsection (E) and accepted by the utility shall not be replaced
with an overhead distribution pole line except upon a verified application of
the utility, as stated in subsection (E)(4)(a).
5. Nonapplicability
a. Any underground electric distribution
system requiring more than single phase service is not covered by this
regulation and shall be constructed pursuant to the effective line extension
rules and regulations or policies of the affected utility on file with the
Commission.
b. If there are one or
more existing distribution pole lines or lines on or across a recorded
subdivision at the time of the application for electrical service for the
subdivision and the line will be utilized in the subdivision. (This would not
apply if the pole line were serving a building or groups of buildings or any
other type of service which would be removed before construction is
finished.)
c. A distribution pole
line that parallels a boundary of a subdivision and this line can serve lots
within the subdivision.
d.
Subdivisions recorded prior to the effective date of this rule shall be
governed by the terms and conditions of subsection (E).
F. Ownership of facilities. Any
facilities installed hereunder shall be the sole property of the
utility.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.