Ariz. Admin. Code § R18-13-1003.02 - Additional Emergency Action Plan Requirements for CCR Surface Impoundments
A. In addition to
the emergency action plan (EAP) requirements in
40 CFR
257.73(a)(3) and
257.74(a)(3), the
EAP shall:
1. Contain a notification chart
showing the priority for notification in an emergency situation. The owner
shall notify local emergency response agencies, affected downstream
populations, county emergency management agencies, and affected flood control
districts;
2. Contain a delineation
of potentially unsafe conditions, evaluation procedures, and triggering events
that require the initiation of partial or full emergency notification
procedures, based on the urgency of the situation; including the following:
a. Sliding of upstream or downstream slopes
or abutments contiguous to the CCR surface impoundment;
b. Sudden subsidence of the top of the CCR
surface impoundment;
c.
Longitudinal or transverse cracking of the top of the CCR surface
impoundment;
d. Unusual release of
water from the downstream slope or face of the CCR surface
impoundment;
e. Other unusual
conditions at the downstream slope of the CCR surface impoundment;
f. Significant landslides in the reservoir
area;
g. Increasing volume of
seepage;
h. Cloudy seepage or
recent deposits of soil at seepage exit points;
i. Sudden cracking or displacement of
concrete in a concrete or masonry CCR surface impoundment spillway or outlet
works;
j. Loss of freeboard or CCR
surface impoundment cross section due to storm wave erosion;
k. Flood waters overtopping an embankment CCR
surface impoundment; or
l. Spillway
backcutting that threatens evacuation of the reservoir.
3. Contain a specific notification procedure
for each emergency situation anticipated;
4. Contain a description of emergency
supplies and resources, equipment access to the site, and alternative means of
communication.
5. Require the owner
to submit a copy of the proposed emergency action plan for review by the
Arizona Division of Emergency Management and all local emergency coordinators
involved in the plan. The owner shall incorporate appropriate recommendations
generated by the reviews and submit the revised emergency action plan to the
Department.
6. Be reviewed and
updated, at a minimum, every year to ensure the information is accurate and to
incorporate changes such as new personnel, changing roles of emergency
agencies, emergency response resources, conditions of the surface impoundment
and information learned from mock exercises. The owner shall send updated
portions of the plan to persons and agencies holding copies of the plan within
15 days after preparation of an update. The updated plan shall be placed in the
facility's operating record as required by § 257.105(f)(6).
7. Notwithstanding paragraph (6) above, the
owner or operator of a CCR surface impoundment may amend the written EAP at any
time provided the revised plan is placed in the facility's operating record as
required by § 257.105(f)(6). The owner or operator must amend the written
EAP whenever there is a change in conditions that would substantially affect
the EAP in effect.
8. Be certified
by a qualified professional engineer stating that the written EAP, and any
subsequent amendment of the EAP, meets the requirements of this
Article.
B. In addition
to the emergency action plan requirements in §§ 257.73(a)(3) and
257.74(a)(3), as incorporated:
1. The owner or
operator shall increase the frequency of observation when the reservoir is
full, during heavy rains or flooding, and following an earthquake.
2. The owner or operator is responsible for
the safety of the CCR surface impoundment and shall take action to lower any
liquid portion of the reservoir if it appears that the impoundment has weakened
or is in danger of failing.
3. The
owner or operator of a CCR surface impoundment shall immediately notify the
Department and responsible authorities in adjacent and downstream communities,
including emergency management authorities, of a condition that may threaten
the safety of the impoundment. The owner shall take necessary actions to
protect human life and property, including action required under an emergency
action plan or order issued under this Article. The owner shall report these
actions to the Director as soon as possible, but not later than 12 hours after
discovery of the conditions.
4. If
CCR surface impoundment failure appears imminent, the owner or operator shall
notify the county sheriff, and the Arizona Department of Public Safety or other
emergency official immediately.
5.
The owner or operator shall notify the Director immediately of any emergency
condition that exists and any emergency action taken.
6. Emergency actions not impairing the safety
of the CCR surface impoundment may be taken before guidance can be provided by
an engineer and do not require prior approval of the Director. Emergency
actions do not excuse an owner's responsibility to promptly undertake a
permanent solution. Emergency actions include:
a. Stockpiling materials such as riprap,
earth fill, sand, sandbags, and plastic sheeting.
b. Lowering the reservoir level by making
releases through the outlet or a gated spillway, by pumping, or by
siphoning.
c. Armoring eroded areas
by placing sandbags, riprap, plastic sheeting, or other available
material.
d. Plugging leakage
entrances on the upstream slope.
e.
Increasing freeboard by placing sandbags or temporary earth fill on the CCR
surface impoundment.
f. Diverting
flood waters to prevent them from entering the reservoir basin.
g. Constructing training berms to control
flood waters.
h. Placing sandbag
ring dikes or reverse filter materials around boils at the downstream toe to
provide back pressure.
i. Removing
obstructions from outlet or spillway flow areas.
7. Emergency actions impairing the safety of
the CCR surface impoundment require prior approval of the Director. An owner
shall not lower the water level by excavating the spillway or embankment unless
failure is imminent.
8. The
Director shall issue an emergency approval to repair, alter, or remove an
existing CCR surface impoundment if the Director finds that immediate remedial
action is necessary to alleviate an imminent threat to human life or property.
a. The emergency approval shall be provided
in writing.
b. The emergency
approval may contain conditions the Director determines are appropriate to
protect human life or property.
c.
The emergency approval is effective immediately for 30 days after notice is
issued unless extended in writing by the Director. The Director shall also send
notice to the county flood control district of the county in which the CCR
surface impoundment is located, all municipalities within five miles downstream
of the CCR surface impoundment, and any additional persons identified in the
emergency action plan.
d. The
Director may institute legal or administrative proceedings that the Director
deems appropriate for violations of the emergency approval or conditions of the
emergency approval.
e. After the
Director issues an emergency approval, the Department shall post information
related to the approval on the Department's CCR website as soon as
practicable.
C.
The requirements in this Section are based on Arizona dam safety standards
additional to those in 40 CFR 257, subpart D, as incorporated in this Article,
and do not apply to:
1. CCR surface
impoundments with a maximum height of less than 6 feet, regardless of storage
capacity;
2. CCR surface
impoundments with a maximum height of between 6 and 25 feet and a storage
capacity of less than 50 acre-feet; or
3. CCR surface impoundments with a maximum
height greater than 25 feet and a storage capacity of 15 acre-feet or
less.